This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.
Blog15 December 2016
Andrews Boilers keep healthcare residential unit functional during refurbishment project
The largest healthcare service in England had plans of undergoing an extensive extension and refurbishment project. However, before this could take place, a temporary boiler was required to provide the residential unit with constant heating while the boiler house underwent a re-fit.
Following an urgent call out, an Andrews engineer visited the location and recommended a 250kW boiler hire unit complete with temporary pipe work.
Logistical problems and a lack of space on the active site made it infeasible to station the temporary boiler near the existing boiler house. Our solution was to position the boiler a short distance away, providing the client with additional hose runs to connect to the existing flow and return stabbings.
The short-term boiler rental proved to be a practical and effective solution, resulting in an extremely satisfied customer. By acting quickly, our specialists were able to ensure the residential unit was supplied with constant heating and hot water until the permanent boiler had been re-instated.